Project 28 : Awba Fertilizer Production Factory (32,352 m²)

Awba Fertilizer Production Factory Site Layout

Project 28 (25th, August, 2016)
Awba Fertilizer Production Factory
Office Building (2 Storeyed) (1,079 m²)
Laboratory Building (322 m²)
SP Formulation Building (532 m²)
SL Formulation Building 1 (1,417 m²)
EC Formulation Building 1 (1,417 m²)
WP Formulation Building (451 m²)
SC Formulation Building (721 m²)

Miscellaneous Workshop (374 m²)
Fire Fighting Pond (1,151 m²)
Waste Water Treatment Building (1,168 m²)
Incinerator Building (130 m²)
Drum Crusher Building (653 m²)
Utility Building 1 (383 m²)
Utility Building 2 (383 m²)
NDG Warehouse 1 (2,728 m²)
NDG Warehouse 2 (2,728 m²)
NDG Warehouse 3 (2,728 m²)
NDG Warehouse 4 (2,728 m²)
NDG Warehouse 5 (2,728 m²)
NDG Warehouse 6 (2,728 m²)
Cafeteria Building (456 m²)
Shower & Locker Building (318 m²)
Car Park Area (352 m²)
SL Formulation Building 2 (1,417 m²)
SC Formulation Building 2 (721 m²)
GR Formulation Building (557 m²)
EC Formulation Building 2 (1,417 m²)
SL Formulation Building 3 (1,417 m²)

Location : Mhaw Bi Tsp, Yangon, Myanmar.
Client : AWBA Co., Ltd.

Nyan Lin Phyoe (B.E Mechanical 2012) nyanlinphyoe.mne@gmail.com I was working as M&E Design Engineer  from 2014-May to 2018-S...